Before we start building the car wash it is imperative to perform due diligence

Proposing Site & Civil Plan

Architect will work on the preliminary drawings to show different ideas of the car wash layout and exterior look. Once decided, Civil Engineer will be involved to work on civil & grading plans.

Application Development Permit

Once site & civil plans finalized, Development Permit application will be submitted to city or town planning department. It will take 6-8 weeks for the city or town’s planning department to get back.

Development Permit Approved

At this point, we will be working on the detailed drawings including, Structural, Electrical & Mechanical.

Application For Building Permit

This will take approximately 6-8 weeks for approval.

Building Permit Approved

To determine if there is any direct competition in and around proposed car wash.

Building Selection

Precast Concrete, Nuform, Steel, Concrete Blocks.